MahaRERA Orders Pune Builder to Pay Interest Over Delayed Possession
The Maharashtra Real Estate Regulatory Authority (MahaRERA) has directed a Pune builder to pay interest to a homebuyer after possession of a flat was delayed and was not offered with an occupancy certificate.
The case involved a homebuyer who had paid ₹39.15 lakh toward a flat priced at ₹41.85 lakh. That ₹39.15 lakh is the amount already paid for the property—not the additional compensation ordered for the delay. The builder’s liability arises from interest on the payment because possession was not delivered as required.
What MahaRERA Ordered in the ₹39.15 Lakh Pune Homebuyer Dispute
MahaRERA rejected the builder’s justification for the delay and directed that interest be calculated from January 1, 2025. The interest will continue until the builder offers possession along with the required occupancy certificate.
The authority also allowed any remaining amount payable by the homebuyer under the agreement to be adjusted against the interest due under the order. This means the ₹39.15 lakh payment is not automatically being treated as a refund or a separate compensation award. Instead, it forms the basis for calculating the delayed-possession interest liability.
The builder had offered ₹35,000 as goodwill compensation without admitting liability. MahaRERA held that this offer did not remove the builder’s legal obligation arising from delayed possession.
Why the Builder Was Held Liable for Delayed Possession
A homebuyer’s obligation to pay under a registered agreement is linked to the developer’s obligation to complete the project and offer possession in accordance with the applicable requirements. A possession offer without an occupancy certificate may not meet that obligation.
In this dispute, MahaRERA found that the builder’s explanation for the delay was insufficient. The authority therefore applied the regulatory remedy for delayed possession rather than treating the ₹35,000 goodwill payment as a full settlement.
The order reinforces an important point for buyers: possession-related disputes are not limited to the date when a developer says a flat is ready. The status of the occupancy certificate and the terms of the registered agreement can also affect whether possession has been validly offered.
How the Delayed-Possession Interest Will Be Calculated
Interest at SBI MCLR Plus Two Percentage Points Until Possession With an Occupancy Certificate
The applicable rate is the State Bank of India marginal cost of lending rate, or MCLR, plus two percentage points. It applies to the amount paid by the homebuyer and runs from January 1, 2025, until possession is offered with an occupancy certificate.
An estimate placed the interest at approximately ₹7.1 lakh up to September 8, 2026. That calculation used a 10.75% rate over 616 days. However, this is an estimate of the interest accruing under the order, not a separately fixed compensation amount awarded by MahaRERA. The final figure may change with the applicable rate, payment adjustments and the date on which compliant possession is offered.
What the Order Means for MahaRERA Homebuyer Compensation Claims
The Pune decision highlights how MahaRERA homebuyer compensation can operate in a delayed-possession case. The key issue is often not simply how much the buyer paid, but whether the developer met its possession obligations and what interest follows when it did not.
Homebuyers facing a similar Pune builder dispute should preserve the registered agreement, payment receipts, correspondence about possession, demand notices and evidence showing the occupancy-certificate status. They should also compare the promised possession date with the actual offer made by the developer.
Facing delayed possession or a builder dispute? Review your payment records, promised possession date and occupancy-certificate status, then seek professional advice on pursuing your MahaRERA homebuyer compensation claim.
